Net metering in the Philippines

How to earn bill credits from the solar power you don’t use, and how to size your system to save the most.

Basahin ang gabay na ito sa Tagalog

What is net metering?

Net metering lets a home or business with grid-connected solar panels send the electricity it doesn’t use to its electric utility (Meralco or your electric cooperative). The utility installs a two-way (bi-directional) meter that records the power you take from the grid and the power you send back.

Each kilowatt-hour (kWh) you send to the grid earns a peso credit, and the credits are used to reduce your electric bill.

Who can apply?

  • Customers of a distribution utility who are in good credit standing (bills paid on time).
  • A renewable energy system of 100 kW or smaller. That covers practically every home and most small businesses.
  • The system must be connected to the grid, so an on-grid or hybrid system qualifies. An off-grid system has no grid connection and cannot export power.

Net metering was created under the Renewable Energy Act of 2008 (Republic Act No. 9513), and its rules are set by the Energy Regulatory Commission (ERC).

How the credits are computed

Exported power is credited at your utility’s blended generation cost. That is only the generation part of your bill, so a kWh you export is worth less than a kWh you would otherwise buy, which also carries distribution, transmission, taxes and other charges.

In practice, solar power you use yourself saves you more than solar power you export. That is why we size systems around how you actually use electricity:

  • Match the panels to your daytime use instead of making the system as big as possible.
  • Run heavy loads such as the washing machine, water pump or air-conditioning while the sun is up.
  • Add a battery (a hybrid system) to store the midday surplus for the evening and for brownouts.

The usual application steps

Each utility has its own forms and checklist, so always get the current list from your utility. Most applications go like this:

  1. Design the system

    Plan an on-grid or hybrid system. The utility will ask for an electrical plan signed by a licensed electrical engineer.

  2. Permits and installation

    Get an electrical permit from your city or municipal office. After installation, the office inspects the work and issues the Certificate of Final Electrical Inspection (CFEI).

  3. Apply to your utility

    Submit the net-metering application with the documents your utility lists.

  4. Evaluation and inspection

    The utility reviews the design and equipment and inspects the installation.

  5. Sign the agreement

    You sign a Net-Metering Agreement with the utility.

  6. Meter installation

    The utility installs the bi-directional meter, and your exports start earning credits.

The rules are changing

The Department of Energy and the ERC have been working to shorten and simplify net-metering applications, and the ERC proposed further changes in 2026. Check the latest requirements with your utility before you apply.

Planning a grid-connected system?

Use our free PV Calculator for a first estimate based on your monthly bill, read about on-grid, hybrid and off-grid systems, or talk to us about your plans.

Sources: Department of Energy, The 5 W’s of Net Metering (primer); Republic Act No. 9513. Last checked October 2026. This guide is general information; your utility’s current rules apply.